A Kentucky homebuyer who tried to withdraw from a nearly $1 million condominium purchase after construction delays has lost his lawsuit seeking to recover his earnest money deposit. The developer argued that it had repeatedly extended the construction deadline under the purchase agreement and that the buyer had cancelled the deal too early. A federal judge has agreed, ruling that the buyer’s termination was ineffective and that the developer was entitled to retain his earnest money deposit.In a November 23, 2026 memorandum opinion and order in David E Segraves v. CPX Boardwalk III, LLC, available on Justia, the US District Court for the Eastern District of Kentucky granted the developer’s motion for summary judgment in part and dismissed Segraves’ complaint with prejudice. The court also allowed the developer’s breach-of-contract counterclaim to proceed to a separate damages hearing.
A $985,000 purchase delayed by construction
The dispute began in November 2022, when David E Segraves signed a purchase agreement with CPX Boardwalk III, LLC, for Unit 420 in a condominium development under construction in Newport, Kentucky. The agreed purchase price was $985,000. The original agreement did not specify a completion date. However, in May 2023, the parties signed an addendum setting March 15, 2024, as the expected completion date.The contract allowed CPX to extend the deadline for delays caused by circumstances beyond its reasonable control, including material shortages, supply chain problems and labour shortages. It also gave the developer discretion to extend the date by up to another 90 days for any reason. On January 31, 2024, CPX notified Segraves that construction challenges would prevent the project from meeting the March deadline. The developer anticipated delivering units in June and July.A second email, sent on May 9, 2024, cited continuing construction delays and difficulties securing qualified workers. CPX said individual closings would begin between August and October. Segraves did not object to either notification. However, on June 21, 2024, he sent a termination notice stating that he no longer wished to proceed with the purchase. He believed the developer had used its 90-day extension and that he was entitled to cancel once that period expired. CPX rejected his termination notice on July 7, 2024.
Buyer challenged the extensions and sought his deposit
Segraves filed a lawsuit in October 2024, arguing that his termination was valid and that he was entitled to the return of his earnest money deposit, along with interest and attorneys’ fees. He also disputed his obligation to pay for upgrades he had selected for the condominium. The upgrades totalled $106,972, with a $6,000 credit, leaving an upgrade deposit of $100,972.Segraves maintained that a CPX representative had told him the upgrade costs could be included in his mortgage. He also argued that the developer had effectively waived the requirement for advance payment. CPX denied that the payment requirement had been waived and filed a counterclaim alleging that Segraves had breached the purchase agreement by attempting to cancel the deal and failing to pay the upgrade deposit.
Judge rules that the cancellation was ineffective
The federal court found that the purchase agreement allowed CPX to extend the completion date repeatedly when qualifying construction delays occurred. It rejected Segraves’ argument that the developer could exercise its extension rights only once.The judge also found that CPX’s January and May 2024 emails sufficiently communicated the construction delays and its intention to extend the deadline. Although the emails did not specify a precise revised completion date or identify the particular extension clause being invoked, they cited construction challenges and labour shortages covered by the agreement’s force majeure provision.The court therefore concluded that CPX had validly exercised its extension rights before receiving Segraves’ June 21 termination notice. His attempt to cancel was consequently premature and constituted a breach of the purchase agreement. Because the termination was ineffective, the court ruled that Segraves was not entitled to recover his earnest money deposit. The agreement expressly made the deposit non-refundable except in circumstances specified in the contract, including a valid and timely termination.The judge also rejected his argument that CPX had waived the upgrade payment requirement. The agreement required amendments to be in writing, and the court found that the alleged oral assurances could not override the contractual payment terms. It therefore held that Segraves was obligated to pay the $100,972 upgrade deposit, although the amount of damages CPX could recover remained to be determined.
Developer resold condominium for $1.275 million
While the lawsuit was pending, Unit 420 received its certificate of occupancy in February 2025. CPX relisted the property in July 2025 for $1.275 million and completed its sale on June 11, 2026. After paying closing costs and a real estate commission of $38,250, the developer received net proceeds of $1,226,816.The judge noted that the gain from the higher resale price could offset any consequential damages claimed by CPX. The court found that CPX had not established its entitlement to compensatory damages at the summary judgment stage, although it could still be entitled to nominal damages. It also found that Segraves had breached his obligation to pay for the selected upgrades, but left the amount of any recoverable damages for a separate hearing.The November 23 order denied Segraves’ motion for summary judgment, granted CPX’s motion in part and dismissed his complaint with prejudice. The developer’s counterclaim remains subject to the forthcoming damages hearing.